Demand Response
WELCOME TO EVEN MORE SAVINGS
How does Demand Response pay?
The electric grid has limited generation capacity, and runs with a set amount of headroom. Some days however are too taxing on the grid. In addition to the normal demand on the system, a heat wave has everyone turning up the AC. This demands more electricity–potentially beyond the system’s capacity, at which point brown-outs and rolling black-outs occur.
To avoid this scenario, a system of incentives exists. This chart illustrates an “Event Day.” When called, the participants voluntarily shift their demand to an alternate time-frame. Here a medium-sized manufacturer shifts some demand to the evening and is awarded more than $6,000.
VIEW OUR FULL PRESENTATION ON DEMAND RESPONSE
WE OFFER ZERO-PENALTY DEMAND RESPONSE
Some or even most demand response programs offer the ability to earn money for participation, but will penalize you if you are unable to perform during an emergency event. Not us. Contact us for a completely free consultation to find out how you may be able to participate.
SMART GRID PROGRAMS
Emergency Demand Response
Demand Reduction (DR, ILR) – Limited, Extended, and Annual
Energy Reduction (Voluntary Participation)
Economic Demand Response
Load Reduction
Synchronized Reserves
Day Ahead Scheduling Reserves
Regulation and Frequency Response
CON EDISON SMART GRID PROGRAM IN THE SPOTLIGHT
DLRP Tier 1 Offer
$18/kW
5+ event bonus pay: $5/kW
Performance Pay Rate: $1.00/kWh
2-Hour Test Each SCP (2)
Notification: 2 Hours
Duration: May 1 – Sep 30
EXAMPLE 4-HOUR EVENT (1)
Reservation Pay: 50kW x 4h x $18 = $3,600
Performance Pay: 50kW x 4h x $1/kWh = $200
Total Payout: $3,800
Settlements paid seasonally
CSRP 4-Boro Offer
$18/kW
5+ event bonus pay: $5/kW
Performance Pay Rate: $1.00/kWh
1-Hour Test Each SCP (2)
Notification: 21 Hours
Duration: May 1 – Sep 30
EXAMPLE 4-HOUR EVENT (1)
Reservation Pay: 50kW x 4h x $18 = $3,600
Performance Pay: 50kW x 4h x $1/kWh = $200
Total Payout: $3,800
Settlements paid seasonally
ASSUMPTIONS FOR DLRP/CSRP TABLE ABOVE
50 kW Commitment
Event Length of 4 hours
Tier 1 DLRP Pay/CSRP Pay
Additional 3-Year incentive available but not shown
CSRP reservation payments of $18/kW for Bronx, Brooklyn, Manhattan, and Queens
CSRP also available for Staten Island and Westchester at a reduced rate of $6/kW
NOTES
SCP – Seasonal Capability Period
REQUIREMENTS & PENALTIES
There are no penalties for non-performance
Non-performance results in de-rating
Performance of 25% or less results in no payment
Customer must have a 15-min ConEd interval meter or AMI Smart Meter
OTHER
CSRP hours vary based on geography
DLRP Tier 2 program for $25/kW